Underground structures of working shaft and pipe jacking tunnels were constructed, where max. excavation depth of shaft reached up to 16m. In hard soil, shaft lining was casted on site with caisson method, ring-by-ring from top to bottom, whereas sinking caisson method was adopted in soft soil.